Construction News

Last Update
29.09.2025
  • Five full floors were built
  • The installation of the sixth floor slab roofing has begun.
Watch Video
20.05.2025
  • Work on Pouring the 5th Floor Begins
  • Work is underway to erect utility shafts.
Watch Video
04.04.2025
  • The Concrete slab of the 4th floor has been porued
  • work on teh construction of communication shafts is in progress.
Watch Video
17.02.2025
  • The Third Floor Slab Was Poured
  • The Fourth Floor Columns Have Been Poured
  • Installation of The Fourth Floor Slab Formwork
  • Teh Road Adjacent to the site Has been Rehabilitated
Watch Video
17.09.2024
  • Pouring of columns of the 3nd floor was performed
Watch Video
3.08.2024
  • The 2st floor has been poured
Watch Video
11.07.2024
  • Pouring of the foundation cushion is completed
  • prepared for puring concrete on the 1st floor
Watch Video
6.05.2024
  • Pouring of the toundation cushion has been completed and work on pouring concrete for the 1st floor columns has begun.
Watch Video
15.04.2024
  • Pouring the foundation cushion
Watch Video
18.03.2024
  • Site preparation and pouring of the foundation cushion has been completed.
  • Successfully passed Accor insection and final inspections by surveyors.
Watch Video
Book Now
Reserve live consultation Now!
Calls are FREE, choose available time, and let us schedule a talk.
Subscribe to learn about our promotions and special offers.
Made on
Tilda