18.09.2025
- At this stage, work is underway on the 7th floor, where blockwork installation is actively in progress
- The process involves 8,000 units of B25-grade concrete and high-strength A500 reinforcement, ensuring the reliability and durability of each floor.
Watch Video
7.07.2025
Tower B
- The reinforcement process of the 13th floor has been completed.
- The slab has been poured of the 13th floor.
- The columns of the 13thh floor are being are constructed.
Watch Video
7.06.2025
Tower B
- 11th floor slab reinforcement is in progress, aligned with the structural engineering plan.
- concrete pouring is scheduled with in the next five working days.
- Vertical stuctural elements (columns and monolithic shear walls) are fully completed.
- Slab formwork installation is finished and ready for the next phase.
- All work is conducted under strict technical supervision and adheres to gith engineering standarts.
Watch Video
7.05.2025
- Installation of columns nad floor slabs on the 11th floor
- construction of internal partitions of the block
Watch Video
7.02.2024
Tower A
- Concrete was poured for the coluns of the 11th floor.
Tower B
- The floor of the 12th floor has been poured.
- Work continues on installing exterior partitions.
Tower C
- Works on construction of internal partitions are in progress.
Watch Video