29.09.2025
- Five full floors were built
- The installation of the sixth floor slab roofing has begun.
Watch Video
20.05.2025
- Work on Pouring the 5th Floor Begins
- Work is underway to erect utility shafts.
Watch Video
04.04.2025
- The Concrete slab of the 4th floor has been porued
- work on teh construction of communication shafts is in progress.
Watch Video
17.02.2025
- The Third Floor Slab Was Poured
- The Fourth Floor Columns Have Been Poured
- Installation of The Fourth Floor Slab Formwork
- Teh Road Adjacent to the site Has been Rehabilitated
Watch Video
17.09.2024
- Pouring of columns of the 3nd floor was performed
Watch Video
11.07.2024
- Pouring of the foundation cushion is completed
- prepared for puring concrete on the 1st floor
Watch Video
6.05.2024
- Pouring of the toundation cushion has been completed and work on pouring concrete for the 1st floor columns has begun.
Watch Video
18.03.2024
- Site preparation and pouring of the foundation cushion has been completed.
- Successfully passed Accor insection and final inspections by surveyors.
Watch Video