5.08.2025
- Installation of facade partitions
- the installation of alumminum curtain walls has been completed.
Watch Video
6.09.2024
Tower A
- Inner work and installation of double glazing is progress
- Facade cladding is in progress
Tower B
- Concrete poured for the columns of the 11th floor and the floor of the 12th floor.
Watch Video
1.08.2024
Tower A
- Inner work and installation of double glazing is progress
- Facade cladding is in progress
Tower B
- Concrete poured for the columns of the 10th floor and the floor of the 11th floor.
Watch Video
19.06.2024
Tower A
- Works on installation of double glazing made of energy-efficient tempered glass in accordance with the Brand standards continue.
- Work on the facade cladding with alucabond continues
Tower B
- Concrete poured for the columns of the 9th floor and the floor of the 10th floor.
Watch Video
14.04.2024
Tower A
- Works on installation of double glazing made of energy-efficient tempered glass in accordance with the Brand standards continue.
- Work on the facade cladding with alucabond continues
Tower B
- Concrete poured for the columns of the 7th floor and the floor of the 8th floor.
Watch Video
8.03.2024
Tower A
- Works on installation of double glazing made of energy-efficient tempered glass in accordance with the Brand standards continue.
- Work on the facade cladding with alucabond is begginning.
- Work continues on pouring soundproofing screeds.
Tower B
- Concrete pouring of columns of the 5th floor and floor of the 6th floor is completed.
- Construction inspection by Accor specialists has been successfully passed.
Watch Video