Construction News

Last Update
18.09.2025
  • At this stage, work is underway on the 7th floor, where blockwork installation is actively in progress
  • The process involves 8,000 units of B25-grade concrete and high-strength A500 reinforcement, ensuring the reliability and durability of each floor.
Watch Video
7.07.2025

Tower B


  • The reinforcement process of the 13th floor has been completed.
  • The slab has been poured of the 13th floor.
  • The columns of the 13thh floor are being are constructed.
Watch Video
7.06.2025

Tower B


  • 11th floor slab reinforcement is in progress, aligned with the structural engineering plan.
  • concrete pouring is scheduled with in the next five working days.
  • Vertical stuctural elements (columns and monolithic shear walls) are fully completed.
  • Slab formwork installation is finished and ready for the next phase.
  • All work is conducted under strict technical supervision and adheres to gith engineering standarts.
Watch Video
7.05.2025
  • Installation of columns nad floor slabs on the 11th floor
  • construction of internal partitions of the block
Watch Video
7.02.2024

Tower A


  • Concrete was poured for the coluns of the 11th floor.

Tower B


  • The floor of the 12th floor has been poured.
  • Work continues on installing exterior partitions.

Tower C


  • Works on construction of internal partitions are in progress.
Watch Video