28.07.2025
  • Block arrangement
  • Partitioning works
показать видео
12.07.2025
  • Explosive works
показать видео
17.03.2025

Tower B


  • The Installation of interior partitions is ongoing
  • The installation of windows is ongoing
  • The installation of elevators is ingoing
показать видео
9.02.2025

Tower B


  • Elevator Installation Process
  • Elevator Installation Beigns
  • Installation Process Elevator Motor
  • Preparatory Work for Balcony Storm Drains
показать видео
2.10.2024

Tower B


  • Elevator Installation Process
  • Elevator Installation Beigns
  • Installation Process Elevator Motor
  • Preparatory Work for Balcony Storm Drains
показать видео
2.10.2024

Tower A


  • The Foundation has been poured
  • Pool area prepared and poured with concrete

Tower B


  • Installation of window facades in progress
  • intarior partitioning works are in progress
  • the elevator shaft is being installed
  • internal communications and sewerage works are in progress

Tower C


  • Site clearance and foundation preparation works have started
показать видео
3.09.2024

Tower A


  • The Foundation has been poured
  • Pool area prepared and poured with concrete

Tower B


  • Installation of window facades in progress
  • interior partitioning works are in progress
  • internal flooring works have been completed.
  • Elevators have been delivered and preparation for installation is underway.
  • Internal communications and sewerage works are in progress
показать видео
15.07.2024

Tower A


  • Foundation pouring works are started
  • Preparation of the territory and pouring of the pool area is performed

Tower B


  • Installation of window facades is in progress.
  • Works on construction of internal partition walls are in progress
  • Floor construction works are completed.
показать видео
15.06.2024

Tower A


  • The foundation has been poured
  • Pool area and poured with concrete

Tower B


  • Installation of window facades is in progress
  • works on construction of internal partition walls are in progress
  • Floor construction works are completed
показать видео
15.05.2024

Tower A


  • Work Continues on the installation of foundation piles.

Tower B


  • Works on installation of window facades continue.
  • Works on construction of internal partition walls are in progress
  • The last 9th has been poured.
показать видео
13.04.2024

Tower B


  • Works on installation of window facades continue.
  • Works on pouring screeds with noise insulation continue.
  • Works on construction of internal partition walls are in progress
показать видео
8.03.2024

Tower A


  • Preparations for pouring the concrete pad for the foundation of tower A were completed.

Tower B


  • Works on installation of window facades continue.
  • Works on pouring screeds with noise insulation continue.
  • Works on internal communications continue
  • The floor has been poured
показать видео
Забронируйте сейчас
Забронируйте онлайн-консультацию прямо сейчас!
Звонки бесплатны — выберите удобное время, и мы организуем разговор
Подпишитесь, чтобы узнавать о наших акциях и специальных предложениях.
(function(w,d,u){ var s=d.createElement('script');s.async=true;s.src=u+'?'+(Date.now()/60000|0); var h=d.getElementsByTagName('script')[0];h.parentNode.insertBefore(s,h); })(window,document,'https://mardicrm.ge/upload/crm/tag/call.tracker.js');