Construction News

Last Update
5.08.2025

  • Installation of facade partitions
  • the installation of alumminum curtain walls has been completed.
Watch Video
6.09.2024

Tower A


  • Inner work and installation of double glazing is progress
  • Facade cladding is in progress

Tower B


  • Concrete poured for the columns of the 11th floor and the floor of the 12th floor.
Watch Video
1.08.2024

Tower A


  • Inner work and installation of double glazing is progress
  • Facade cladding is in progress

Tower B


  • Concrete poured for the columns of the 10th floor and the floor of the 11th floor.
Watch Video
19.06.2024

Tower A


  • Works on installation of double glazing made of energy-efficient tempered glass in accordance with the Brand standards continue.
  • Work on the facade cladding with alucabond continues

Tower B


  • Concrete poured for the columns of the 9th floor and the floor of the 10th floor.
Watch Video
14.04.2024

Tower A


  • Works on installation of double glazing made of energy-efficient tempered glass in accordance with the Brand standards continue.
  • Work on the facade cladding with alucabond continues

Tower B


  • Concrete poured for the columns of the 7th floor and the floor of the 8th floor.
Watch Video
8.03.2024

Tower A


  • Works on installation of double glazing made of energy-efficient tempered glass in accordance with the Brand standards continue.
  • Work on the facade cladding with alucabond is begginning.
  • Work continues on pouring soundproofing screeds.

Tower B


  • Concrete pouring of columns of the 5th floor and floor of the 6th floor is completed.
  • Construction inspection by Accor specialists has been successfully passed.
Watch Video